Scope

Scope

The first major subterranean transit expansion in San Francisco ​for over 40 years, this new light rail system will link AT&T Park with Chinatown.  Future construction will continue on to the northern extends of the city.

​Four new stations (one surface, three subsurface) are to be constructed over the 1.5 mile route.​

Agency Coordination

Agency Coordination

The project included intensive planning and coordination with all aspects of the city's infrastructure and labyrinth of governing agencies. 

Virtual Design Coordination

Virtual Design Coordination

All building systems and engineering modeled in Revit or 3D Civil.  Coordination accomplished with Navisworks.

Moscone Early.jpg
Headhouse

Headhouse

MOS 100          217 - Plans_Page_2.jpg
ALT HHS 3 - persp - fourth st.jpg
Pages from MOS 100          317-3_Page_3.jpg
ALT HH 2 Headhouse up Skylight.jpg
110428 ALT HH looking back.jpg
final CS MOS Axon - 02 Concourse (screen).jpg
ALT HH 2 - Ticketing.jpg
MOS 100          417 - Plans_Page_4.jpg
final CS MOS Concourse - From Fare Gates - Early.jpg
MOS Rendering - Concourse - East Wall - Looking North - 111108.jpg
final CS MOS Construction - Shoring.jpg
MOS Rendering - Concourse - Centerline - Looking North - 111108.jpg
final CS MOS Axon - 01 Platform (screen).jpg
MOS 100          517 - Plans_Page_5.jpg
final CS MOS Platform - Kiosk - Oblique - Train Approaching.jpg
Pages from MOS 100          417-3_Page_4.jpg
final CS MOS Construction - Slurry Wall Cutting Head.jpg
robbins_mom_chung_web.jpg
White.jpg

San Francisco Municpal Transportation Agency Central Subway

Senior Project Manager/Designer   |   1.7 mi / 2.7 km | $1.5B   |   w. Central Subway Design Group

Scope

The first major subterranean transit expansion in San Francisco ​for over 40 years, this new light rail system will link AT&T Park with Chinatown.  Future construction will continue on to the northern extends of the city.

​Four new stations (one surface, three subsurface) are to be constructed over the 1.5 mile route.​

Agency Coordination

The project included intensive planning and coordination with all aspects of the city's infrastructure and labyrinth of governing agencies. 

Virtual Design Coordination

All building systems and engineering modeled in Revit or 3D Civil.  Coordination accomplished with Navisworks.

Headhouse

San Francisco Municpal Transportation Agency Central Subway
Scope
Agency Coordination
Virtual Design Coordination
Moscone Early.jpg
Headhouse
MOS 100          217 - Plans_Page_2.jpg
ALT HHS 3 - persp - fourth st.jpg
Pages from MOS 100          317-3_Page_3.jpg
ALT HH 2 Headhouse up Skylight.jpg
110428 ALT HH looking back.jpg
final CS MOS Axon - 02 Concourse (screen).jpg
ALT HH 2 - Ticketing.jpg
MOS 100          417 - Plans_Page_4.jpg
final CS MOS Concourse - From Fare Gates - Early.jpg
MOS Rendering - Concourse - East Wall - Looking North - 111108.jpg
final CS MOS Construction - Shoring.jpg
MOS Rendering - Concourse - Centerline - Looking North - 111108.jpg
final CS MOS Axon - 01 Platform (screen).jpg
MOS 100          517 - Plans_Page_5.jpg
final CS MOS Platform - Kiosk - Oblique - Train Approaching.jpg
Pages from MOS 100          417-3_Page_4.jpg
final CS MOS Construction - Slurry Wall Cutting Head.jpg
robbins_mom_chung_web.jpg
White.jpg